Question: Consider a sequential process with 3 stations. The processing time ( minutes per unit by 1 employee ) and number of employees at each station
Consider a sequential process with stations. The processing time minutes per unit by employee and number of employees at each station are as follows:
tableProcessing time,Number of EmployeesStation A: unit, employees,Station B: unit, employees,Station C: unit, employees,
What is the bottleneck?
Station A
Station B
Station C