Question: Question 2 . ( Crash Partayyyy ) Assume the network and data that follow: a . Construct the network diagram when Normal Time ( Weeks

Question 2.(Crash Partayyyy)
Assume the network and data that follow:
a. Construct the network diagram when "Normal Time (Weeks)" are used for activity duration.
b. What is the earliest time that the project can be completed without crashing? What is the critical path? Compute the slack of each activity.
c. Determine which activities should be crashed, and the total cost of crashing, if the goal is to shorten the project by three weeks as cheaply as possible.
d. Suppose that the time to complete activities B, C, and G for the above network is variable, but that for the remaining activities is not variable. Under the assumption that an activity time has a beta distribution, the path duration times are independent,the three time estimates (in weeks) are:
What is the probability that the project (without crashing) will be completed within 18 weeks or less?
Question 2 . ( Crash Partayyyy ) Assume the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!