Question: Question 2 . ( Crash Partayyyy ) Assume the network and data that follow: a . Construct the network diagram when Normal Time ( Weeks
Question Crash Partayyyy
Assume the network and data that follow:
a Construct the network diagram when "Normal Time Weeks are used for activity duration.
b What is the earliest time that the project can be completed without crashing? What is the critical path? Compute the slack of each activity.
c Determine which activities should be crashed, and the total cost of crashing, if the goal is to shorten the project by three weeks as cheaply as possible.
d Suppose that the time to complete activities B C and G for the above network is variable, but that for the remaining activities is not variable. Under the assumption that an activity time has a beta distribution, the path duration times are independent,the three time estimates in weeks are:
What is the probability that the project without crashing will be completed within weeks or less?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock