Question: Assume the network and data that follow: a. Construct the network diagram. b. Indicate the critical path when normal activity times are used. c. Compute
Assume the network and data that follow:
.png)
a. Construct the network diagram.
b. Indicate the critical path when normal activity times are used.
c. Compute the minimum total direct cost for each project duration based on the cost associated with each activity. Consider durations of 13, 14, 15, 16, 17, and 18 weeks.
d. If the indirect costs for each project duration are $ 400 (18 weeks), $ 350 ( 17 weeks), $ 300 ( 16 weeks), $ 250 ( 15 weeks), $ 200 ( 14 weeks), and $ 150 ( 13 weeks), what is the total project cost for each duration? Indicate the minimum total project costduration.
NORMAL NORMAL CRASH TIME CRASH CosT IMMEDIATE ACTIVITY TIME (WEEKS Cos(WEEKS) PREDECESSORS S 50 70 100 100 S 70 160 110 80 130 100 150 4 4 4 C,E, F
Step by Step Solution
3.49 Rating (159 Votes )
There are 3 Steps involved in it
a Activity Normal Time NT Crash Time CT Normal Cost NC Crash Cost CC NTCT Costweek to expedite A 2 1 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
287-B-M-L-S-C-M (1311).docx
120 KBs Word File
