QUESTION 2 EARNED VALUE AND RESOURCE PLANNING (25 Marks)
2.1 Earned value management helps you quantify the performance of a project. It compares costs and schedules to a baseline to determine if the project is on track. (Project Plan 365, n.d.). Based on this description, analyses the project performance, based on data provided below and answer the following questions:
Estimate At Completion (EAC)
$40 622 917
Actual Cost of Work Performed (ACWP)
$1 667
Budgeted Cost of Work Performed (BCWP)
$2 000
a) What is the earned value of the project if the current percentage complete is 35%, estimate at completion is $40 622 917, actual cost of work performed is $1 667, and the budgeted cost of work performed is $2 000. (5 Marks)
b) Analyse the project performance based on the values and answer given from the previous question a). (5 Marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!