Question: Question 2. Find sequence for minimizing Cmax for 5 jobs which requires four operations in series. There are five machines in the shop as indicated

Question 2. Find sequence for minimizing Cmax for

Question 2. Find sequence for minimizing Cmax for 5 jobs which requires four operations in series. There are five machines in the shop as indicated in figure below. There is choice of machines between M3 and M4 for third operation. All machines processes one job at a time. The processing times requires for every operation on jobs are given in the table: Route 1 M3 MI M2 MS Route 2 M4 Operation 1 Operation 2 Operation 3 Operation 4 2 Jobs Plj P2j P3j 1 65 78 58 41 83 56 19 72 3 15 60 39 63 4 71 75 51 14 5 74 40 31 15 P4j