Question: Question 2 Item# What is needed # Quantity needed Item# On hand (beginning) inventory # Lot sizing# Lead time CBB A A 1 A
Question 2 Item# What is needed # Quantity needed Item# On hand (beginning) inventory # Lot sizing# Lead time CBB A A 1 A 1 B 2 C 65 100 140 L4L 1 L4L 1 25 2 Week 357 Gross req. 40 20 150 C Att 34 5 pts The three tables shows the master production schedule and the bill of materials of part A, and the inventory records of all the parts. There are no scheduled receipts. Given this information, what is the planned order release of part A in Week 6?(Only enter a number. Do not enter any units. (c)orsdemir. Copyrighted content. Cannot be posted.)