Question: Question 2 of 30 Question 2 4 points Save Answer (CH 7) A project was estimated to cost AED 1.5M and scheduled to last for

Question 2 of 30 Question 2 4 points Save Answer
Question 2 of 30 Question 2 4 points Save Answer (CH 7) A project was estimated to cost AED 1.5M and scheduled to last for 6 months. After three months, what would be the schedule Variance given the following earned value analysis in AED? IV - AED 650,000 PV - AED 750,000 AC - AED 800,000 a. -100,000 b. +100,000 OC -50,000 d. +50,000 Moving to another question will save this response. Question 2 of 30 >>