Question: PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which

PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed:

Activity Duration (weeks) Immediate Predecessor(s)
A A -
B B A
C C A
D D A
E E A
F F B,C
G G D,E
H H

F,G

1. What is the overall duration of the project (in weeks)? 2. What is the earliest week you could start activity (E)*(S)? (Write the week number in the field below.) 3. What is the earliest week you could finish activity (E)*(F)? 4. What is the latest week you could start activity (L)*(S)? 5. What is the latest week you could finish activity (L)*(F)? 6. What is the slack time for activity ((((s)*(l))*(a))*(c))*(k)? 7. What would be the overall duration of the project if activity ((((((((d)*(e))*(l))*(a))*(y))*2.0)*(a))*(c))*(t) were increased by (((((((((d)*(e))*(l))*(a))*(y))*2.0)*(t))*(i))*(m))*2.718281828459045 weeks, from (((o)*(l))*(d))*2.0 to $new2(details...) weeks? weeks 8. What would be the overall duration of the project if activity ((((((((d)*(e))*(l))*(a))*(y))*3.0)*(a))*(c))*(t) were increased by (((((((((d)*(e))*(l))*(a))*(y))*3.0)*(t))*(i))*(m))*2.718281828459045 weeks, from (((o)*(l))*(d))*3.0 to $new3(details...) weeks? weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!