Question: PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which
PM.57 The activities needed to develop a new software application are listed in the following table with the activity times and their order in which the activities need to be performed:
| Activity | Duration (weeks) | Immediate Predecessor(s) |
|---|---|---|
| A | A | - |
| B | B | A |
| C | C | A |
| D | D | A |
| E | E | A |
| F | F | B,C |
| G | G | D,E |
| H | H | F,G |
1. What is the overall duration of the project (in weeks)? 2. What is the earliest week you could start activity (E)*(S)? (Write the week number in the field below.) 3. What is the earliest week you could finish activity (E)*(F)? 4. What is the latest week you could start activity (L)*(S)? 5. What is the latest week you could finish activity (L)*(F)? 6. What is the slack time for activity ((((s)*(l))*(a))*(c))*(k)? 7. What would be the overall duration of the project if activity ((((((((d)*(e))*(l))*(a))*(y))*2.0)*(a))*(c))*(t) were increased by (((((((((d)*(e))*(l))*(a))*(y))*2.0)*(t))*(i))*(m))*2.718281828459045 weeks, from (((o)*(l))*(d))*2.0 to $new2(details...) weeks? weeks 8. What would be the overall duration of the project if activity ((((((((d)*(e))*(l))*(a))*(y))*3.0)*(a))*(c))*(t) were increased by (((((((((d)*(e))*(l))*(a))*(y))*3.0)*(t))*(i))*(m))*2.718281828459045 weeks, from (((o)*(l))*(d))*3.0 to $new3(details...) weeks? weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts