Question: QUESTION 2 Processing Time (in Hours) Opl Op2 Op3 Order Op4 Order Quantity 100 4 2 1 4 B 2xxx 10 4 1 2 2

QUESTION 2 Processing Time (in Hours) Opl Op2 Op3

QUESTION 2 Processing Time (in Hours) Opl Op2 Op3 Order Op4 Order Quantity 100 4 2 1 4 B 2xxx 10 4 1 2 2 3 Shipping Due Date Hours remaining Day 5 32 Day 7 48 Day 6 40 Day 5 32 Day 6 40 3xxx 50 6 1 4 D 4xxx 30 8 3 1 6 E 5xxx 100 2 3 For the above table, which job should be scheduled first based on "Slack Per Operation'? A O E