Question: Question 2: Six jobs must be processed through machine A and then machine B as shown below. The processing time for each job is also

Question 2:

  1. Six jobs must be processed through machine A and then machine B as shown below. The processing time for each job is also shown:

Job Number

A

B

C

D

E

F

Machine A minutes A

6

9

7

5

10

3

Machine B minutes B

8

2

7

10

4

7

Find the best way to sequence these jobs (use Johnsons rule).

Prepare a Gantt chart.

Find the efficiency of the schedule

  1. Find the optimal schedule to meet the following requirements for Monday to Sunday:

6, 5, 2, 7, 5, 2, 6. All employees are full time and they work for five consecutive days.

Remember to calculate the efficiency of your schedule (use Tibrewalas rule).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!