Question: Question 2: Six jobs must be processed through machine A and then machine B as shown below. The processing time for each job is also
Question 2:
- Six jobs must be processed through machine A and then machine B as shown below. The processing time for each job is also shown:
| Job Number | A | B | C | D | E | F |
| Machine A minutes A | 6 | 9 | 7 | 5 | 10 | 3 |
| Machine B minutes B | 8 | 2 | 7 | 10 | 4 | 7 |
Find the best way to sequence these jobs (use Johnsons rule).
Prepare a Gantt chart.
Find the efficiency of the schedule
- Find the optimal schedule to meet the following requirements for Monday to Sunday:
6, 5, 2, 7, 5, 2, 6. All employees are full time and they work for five consecutive days.
Remember to calculate the efficiency of your schedule (use Tibrewalas rule).
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts