Question: Question 2 The following represents a project that should be scheduled using CPM: Time estimate (days) Activity Activity predecessor a m b A - 4
Question 2
The following represents a project that should be scheduled using CPM:
|
| Time estimate (days) | ||
Activity | Activity predecessor | a | m | b |
A | - | 4 | 6 | 8 |
B | A | 3 | 5 | 8 |
C | A | 3 | 6 | 10 |
D | A | 3 | 6 | 10 |
E | B, C | 3 | 6 | 8 |
F | B, C | 3 | 5 | 10 |
G | F | 4 | 6 | 10 |
H | F, E, D | 5 | 6 | 8 |
a. Draw the network and show the ES, EF, LS and LF.
b. What is the critical path?
Step by Step Solution