Question: Question 2 The following represents a project that should be scheduled using CPM: Time estimate (days) Activity Activity predecessor a m b A - 4

Question 2

The following represents a project that should be scheduled using CPM:

Time estimate (days)

Activity

Activity predecessor

a

m

b

A

-

4

6

8

B

A

3

5

8

C

A

3

6

10

D

A

3

6

10

E

B, C

3

6

8

F

B, C

3

5

10

G

F

4

6

10

H

F, E, D

5

6

8

a. Draw the network and show the ES, EF, LS and LF.

b. What is the critical path?