Question: The following represents a project that should be scheduled using CPM: Time estimate (days) Activity Activity predecessor a m b A - 4 6 8
The following represents a project that should be scheduled using CPM:
| Time estimate (days) | ||||
| Activity | Activity predecessor | a | m | b |
| A | - | 4 | 6 | 8 |
| B | A | 3 | 5 | 8 |
| C | A | 3 | 6 | 10 |
| D | A | 3 | 6 | 10 |
| E | B, C | 3 | 6 | 8 |
| F | B, C | 3 | 5 | 10 |
| G | F | 4 | 6 | 10 |
| H | F, E, D | 5 | 6 | 8 |
a. Draw the network and show the ES, EF, LS and LF.
b. What is the critical path?