Question: Question 2 Three-point estimating Instead of providing activity estimates as a discrete number, such as four weeks, its often helpful to create a three-point estimate.
Question 2
Three-point estimating
Instead of providing activity estimates as a discrete number, such as four weeks, its often helpful to create a three-point estimate. An estimate that includes an optimistic, most likely, and pessimistic estimate.
-Optimistic (to) -Most Likely (tm) -Pessimistic (tp)
Use the following equation to calculate the expected duration:
Beta Distribution
For Activity A:
Optimistic = 4 hours , Most Likely = 8 hours , Pessimistic = 16 hours
The Standard Deviation is a measure of variability from the mean and is defined as (p - o)/6 so in the example above
Calculate the three point estimate and the standard deviation of activity A. Explain your answer.