Question: QUESTION 2 Using the information given in the table do the following Predecessors b 7 2 A D E F 9 Activity a 1 2.


QUESTION 2 Using the information given in the table do the following Predecessors b 7 2 A D E F 9 Activity a 1 2. 2 3 4 0 3 4 2 5 4 6 0 6 5 8 6 9 A C.B C.B D.E3 -5. 21 Draw the network in AON (activity on node) format PRE4011 OCT/NOV 2018 (6) 2. Calculate the earliest start, earliest finish, latest start and latest finish times for each activity (7) 23 Determine the slack for each activity (3) 24 Determine the critical path and expected completion time (3) [19]