Question: QUESTION 2 With reference to the table below, determine the activities that are on the critical path and the expected time in which the project

QUESTION 2 With reference to the table below, determine the activities that are on the critical path and the expected time in which the project will be completed. Preceding Activity A B C D E F G H J A A A B B C, F D H G, I E, J Optimisti cTime 7 2 8 3 6 2 2 6 4 2 Probable Time 10 2 12 5 6 8 3 2 8 5 Pessimistic Time 19 8 16 10 8 10 8 16 14 8 (20 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!