Question: re to search QUESTION 2 With reference to the table below, determine the activities that are on the critical path and the expected time in
re to search QUESTION 2 With reference to the table below, determine the activities that are on the critical path and the expected time in which the project will be completed. Activity A B C D E F G H J K Preceding A A A C, F O H G, I Optimisti cTime 7 2 8 3 4 6 2 2 6 4 Probable Time 10 2 12 5 8 3 2 8 6 Pessimistic Time 19 8 16 10 8 10 4 8 16 14 8 (20 marks)