Question: Question 2 You are the project manager on a project that has $800,000 software development effort. There are two teams of programmers that will work

Question 2 You are the project manager on a
Question 2 You are the project manager on a project that has $800,000 software development effort. There are two teams of programmers that will work for 6 months a total of 10,000 hours. According to the project schedule your team should be done with 38% of the work. As of today project is 40% complete while 50% budget have been used. Calculate PV, EV, AC, Cost Variance (CV), Schedule Variance (SV) Cost Performance Index (CPI) & Schedule Performance Index (SPI) Analyze the parameters and comment on the status of the project