Question: Question 1. Compute SPI, CPI Estimate At Completion (EAC) and Variance At Completion (VAC) if both SPI and CPI influence the project work when given

Question 1. Compute SPI, CPI Estimate At Completion (EAC) and Variance At Completion (VAC) if both SPI and CPI influence the project work when given variables are Budget At Completion (BAC) = $40,000 Earned Value (EV) = $26,000 Planned Value (PV) = $20,000 Actual Cost (AC) = $25,000 Question 2. You are the project manager on a project that has $500,000 software development effort. There are two teams of programmers that will work for six month for a total of 8,000 hours. According to the project schedule your team should be done with 48% of the work. As of today, the project is 30% complete while 60% budget has been used. Calculate and share your conclusion

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!