Question: Question 21 B 5 D7 G 2 A5 C3 E5 F3 Which activities have positive slack time? O A, B, E, F, G C and

Question 21 B 5 D7 G 2 A5 C3 E5 F3 Which
Question 21 B 5 D7 G 2 A5 C3 E5 F3 Which activities have positive slack time? O A, B, E, F, G C and D OB,D,G B and D