Question: Question 23 (1 point) The following list represents CPM network of a project. 10 Normal time Crash time Normal cost Activity Crash cost Predecessor (day)

Question 23 (1 point) The following list

Question 23 (1 point) The following list represents CPM network of a project. 10 Normal time Crash time Normal cost Activity Crash cost Predecessor (day) (days) $1,000 $1,600 $2,000 $2,600 $500 $1,000 A $4,000 $4,200 A,B $3,000 $4,000 C,D Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? ONAN OC; $100 OD; $100 OE; $1000 OB; $200