Question: Question 23 (1 point) Why should a Project Manager review both earliest completion and latest completion when project scheduling? To determine alternate critical paths To

Question 23 (1 point) Why should a Project
Question 23 (1 point) Why should a Project Manager review both earliest completion and latest completion when project scheduling? To determine alternate critical paths To identify where there are activities that may be temporarily delayed To reallocate resources among project activities To confirm that estimated duration times are correct Question 24 (1 point) A work activity is bursting into the next two following work activities. What action should the Project Manager NOT undertake at the burst point