Question: Question 23 3 pts Given the following activity network: A2 1 Activity A1 takes 6 weeks, A2 takes 8 weeks, and A3 takes 3 weeks.

Question 23 3 pts Given the following activity

Question 23 3 pts Given the following activity network: A2 1 Activity A1 takes 6 weeks, A2 takes 8 weeks, and A3 takes 3 weeks. What is the earliest start time of A3? weeks (round to the nearest integer) Previous Next >