Question: Question 23: Bullet Points A software development project has the following financial details: Total Budget: $1,500,000 Actual Costs to Date: $800,000 Planned Value (PV) to


Question 23: Bullet Points

A software development project has the following financial details:

  • Total Budget: $1,500,000
  • Actual Costs to Date: $800,000
  • Planned Value (PV) to Date: $850,000
  • Earned Value (EV) to Date: $750,000

Questions:

  1. Calculate the Cost Performance Index (CPI).
  2. Calculate the Schedule Performance Index (SPI).
  3. Discuss the implications of the CPI and SPI values for the project.