Question: QUESTION 23 The critical path for a project has the following activities: A(mean= 5, standard deviation= 2) B(mean= 5, standard deviation= 3) C(mean= 5, standard
QUESTION 23
-
The critical path for a project has the following activities:
A(mean= 5, standard deviation= 2)
B(mean= 5, standard deviation= 3)
C(mean= 5, standard deviation= 4)
D(mean= 5, standard deviation= 5)
The mean and standard deviation of the critical path duration respectively is:
A. 20 and 7.3
B. 20 and 14
C. 5 and 14
D. 20 and 54