QUESTION 23

  1. The critical path for a project has the following activities:

    A(mean= 5, standard deviation= 2)

    B(mean= 5, standard deviation= 3)

    C(mean= 5, standard deviation= 4)

    D(mean= 5, standard deviation= 5)

    The mean and standard deviation of the critical path duration respectively is:

    A.

    20 and 7.3

    B.

    20 and 14

    C.

    5 and 14

    D.

    20 and 54