Question: Question 24 (1 point) The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the

Question 24 (1 point) The following table shows
Question 24 (1 point) The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the crash time of all activities are zero. Duration (normal time in days) Crash cost per day Activity Immediate predecessor A 3 $120 B 5 A $85 2 B $50 D 13 A $80 E 8 B.D $200 What is the cost for crashing the project by 2 days