Question: Question 14 (1 point) The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the

Question 14 (1 point) The following table shows
Question 14 (1 point) The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the crash time of all activities are zero: Immediate Activity Duration (days) predecessor Crash cost per period A 2 $100 B 3 A $150 5 $120 D 11 $30 E 7 $400 F 13 E $230 What is the cost for crashing the project by 1 day? Your Answer: 6