Question: QUESTION 24 Please use the following attachment to answer Question 24 What is the approximate forecast for May using a four-month moving average? A. 44
QUESTION 24
Please use the following attachment to answer Question 24
What is the approximate forecast for May using a four-month moving average?
A. 44
B. 38
C. 47
D. 42
E. 45
QUESTION 25
A project task has an early start time of 4, a late start time of 9, an early finish time of 7, and a late finish time of 12. What is the task's slack?
A. 9
B. 6
C. 5
D. 4
E. 0
F. 7

QUESTION 24 4 points Save Answer What is the approximate forecast for May using a four-month moving average? Nov. Dec. Jan. Feb. Mar. April 39 36 44 42 48 46 O A. 44 O B. 38 O C. 47 O D. 42 O E. 45 QUESTION 25 4 points Save Answer A project task has an early start time of 4, a late start time of 9, an early finish time of 7, and a late finish time of 12. What is the task's slack? O A. 9 O B. 6 O C. 5 OD. 4 OE. O OF. 7