Question: Question 25 1 points Using the table answer the following question Activity Immediate Predecessor Time (weeks) B D E 12 8 16 10 14 B,C
Question 25 1 points Using the table answer the following question Activity Immediate Predecessor Time (weeks) B D E 12 8 16 10 14 B,C The project described has a critical path of? 3. 44 b. 24 O c. 40 Od. 60