Question: Activity Q on a project has exactly 4 successors E, F, G, and H whose late start days are 20, 12, 38, and 32. (Here

 Activity Q on a project has exactly 4 successors E, F,

Activity Q on a project has exactly 4 successors E, F, G, and H whose late start days are 20, 12, 38, and 32. (Here "day" means days after project start and successor in this context means that E, F, G, and H are all dependent on Q.) What is the late finish day of Q? Question 27 options: 19 20 37 11