Question: Question 28 3p Given the following activity network: As 4 Az As A Activity Al takes 3 weeks, A2 takes 8 weeks, A3 takes 5

Question 28 3p Given the following activity
Question 28 3p Given the following activity network: As 4 Az As A Activity Al takes 3 weeks, A2 takes 8 weeks, A3 takes 5 weeks, A4 takes 9 weeks, A5 takes 4 weeks. What is the slack time of A3? weeks (roond to the nearest integer)