Question: Question 29 3 Given the following activity network Az As A Az A, A4 A Activity A1 takes 3 weeks, A2 takes 8 weeks, A3

Question 29 3 Given the following activity
Question 29 3 Given the following activity network Az As A Az A, A4 A Activity A1 takes 3 weeks, A2 takes 8 weeks, A3 takes 10 weeks, A4 takes 9 weeks, A5 takes 2 weeks, A6 takes 4 weeks, A7 takes 4 weeks, What is the critical path of the project? O AL A2, A3, A4, A5, A6, A7 A1, A2, A4, A6, A7 A1, A2, A3, A5, A7 1, 2, 3, A6, 7