Question: Question 28 (4 points) One project has 45 activities, 19 of which are on the critical path. The estimated average time for the critical path

Question 28 (4 points) One project has 45

Question 28 (4 points) One project has 45 activities, 19 of which are on the critical path. The estimated average time for the critical path is 120 days. The standard deviation along the critical path is 8. Please choose the correct answer by using PERT analysis. What is the probability that the project can be completed AFTER 125? 0.7340 0.2660 0.3085 0.4255