Question: Question 28 (CH4) The project charter is important for which of the following reasons? It authorizes the sponsor. b. It names the project manager and
Question 28 (CH4) The project charter is important for which of the following reasons? It authorizes the sponsor. b. It names the project manager and authorizes the project manager to use the organization's resources for the project. C. It identifies all the stakeholders. d. It analyzes the stakeholders