Question: Question 29 (2 points) For an activity (in a CPM chart, the Early Start tilne is 8 and the Late Start time is 10. Which

Question 29 (2 points) For an activity (in a CPM
Question 29 (2 points) For an activity (in a CPM chart, the Early Start tilne is 8 and the Late Start time is 10. Which of the following statements is true? 000 b The duration of the work at that point is 2 The process has a slack time of 2 The early finish of the task will be at time 10 Activity is on the critical path