Question: Question 1 8 1 pts For an activity in a CPM analysis, the early start time is 2 1 and the late finish time is

Question 18
1 pts
For an activity in a CPM analysis, the early start time is 21 and the late finish time is 29. Which of the following statements is true?
The activity is on the critical path.
The late start is 27.
The slack for this activity is 8.
The slack time cannot be determined using this information.
The early finish is 19.