Question: Question 3 Given the following activity network: A2 A1 A3 Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 3 weeks with

Question 3 Given the following activity network:

Question 3 Given the following activity network: A2 A1 A3 Activity A1 takes 5 weeks, A2 takes 7 weeks, and A3 takes 3 weeks with a 50% probability and 9 weeks with a 50% probability. Wha situations and then compute the expected project completion time). 8 12 13 14