Question: Question 29 (3 points) Given the portion of the network shown above, what is the earliest finish time for activity D, if the earliest start


Question 29 (3 points) Given the portion of the network shown above, what is the earliest finish time for activity D, if the earliest start time of A is 12 and the earliest start time of B is 13? a) 22 ( b) 23 O c) 24 O d) 25 O e ) 26