Question: Given the portion of the network shown below, what is the earliest finish time for activity F, if the earliest start time of A is

 Given the portion of the network shown below, what is the

Given the portion of the network shown below, what is the earliest finish time for activity F, if the earliest start time of A is 8 and the earliest start time of B is 11 ? A) 4 B) 15 C) 31 D) None of these