Question: Question 29 In the image below, how long is the critical path through this project? Not yet answered Polats out of 10 F Flag question

Question 29 In the image below, how long is the critical path through this project? Not yet answered Polats out of 10 F Flag question Task D 3 days Task E 3 days Start Task A 3 days Finish Task B 2 days Task c 4 days Select one: O a. 3 days O b. 6 days O c. 8 days O d. 9 days Question 30 Calculating a proposed project's expected net monetary gains or losses from that project by discounting the future cash inflows/outflows is known as the selection process Not yet answered Points out of 10 Flag question Select one O a. Internal rate of retum O b. Net scoring model O c. Return on investment O d. Net present value Queron 31 A project's is defined as the orginal scope, cost and schedule. Not yet answered Points out of 10 Select one: a Standard Flag question Ob Benchmark O c Milestone O d. Baseline O HE 30