Question: Question 3 . ( 1 . 0 point ) For the following project, apply the PERT method to find the project duration. Also, answer the

Question 3.(1.0 point)
For the following project, apply the PERT method to find the project duration. Also, answer the following questions.
What is the probability of the project finishing in 35 days?
What is the probability of the project finishing in 48 days?
What is the project duration with a 95% confidence level?
\table[[Activities,Predecessors,Ta (Days),Tm Days,Tb (Days),Mean (),Variance (V)],[A,None,3,4,5,,],[B,A (FS),7,10,19,,],[C,B (FS),4,6,8,,],[D,B (FS),4,7,10,,],[E,C (FS),11,14,23,,],[F,D (FS),6,8,16,,],[G,E, F (FS),2,4,6,,]]
 Question 3.(1.0 point) For the following project, apply the PERT method

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!