Question: Question: 3 ( 1 0 points ) ( CLO - 3 , PLQ ) A toy manufacturer performs the following final operations before stocking it

Question: 3(10 points)
(CLO-3, PLQ)
A toy manufacturer performs the following final operations before stocking it for sal. process consists of four steps.
Step 1: Arrange a set of four parts in a pallet (8 minutes)
Step 2: The pallet moves to the next station where the parts are pre-treated (12 ivinul...
Step 3: Pre-treated parts are assembled (20 minutes)
Step 4: The toys are inspected and packed (5 minutes)
a) What is the cycle time?
b) What is the daily output of this toy manufacturing process if they have 8 hous werkling schedule?
e) What is the utilization of each work station?
d) What is the idle time in each work station?
e) Suppose that a second parallel machine is added at station 3. What is the new cyci. of the system? How did the addition of the second machine at workstation 3 affect the performance of the work cell?
 Question: 3(10 points) (CLO-3, PLQ) A toy manufacturer performs the following

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!