Question: Question 3 10 pts Using the same table data from the one above. Minimum durations and crash costs have been added. The network diagram is

Question 3 10 pts Using the same table data from

Question 3 10 pts Using the same table data from the one above. Minimum durations and crash costs have been added. The network diagram is unchanged. The project incurs weekly administrative costs of $1,300. Normal Minimum Crash Activity Predecessors Duration Duration Cost 6 5 $150 9 8 $350 $750 $300 $275 5 $50 H I D CEF CF 17 14 11 14 14 8 $500 . $325 I KH 2 2 . How much is your cumulative net gain? 1150 1950 2475 2925