Question 3: (18 points) Ten tasks need to be assigned to work stations. The precedence relationship and the time needed for each task are given in the following table (unit is minutes). The throughput requirement is 40 items per hour. Use the largest candidate rule method to balance the line. What is the efficiency? Precedence requirement Task 1 2 3 4. 5 6 7 8 9 10 Time 0.65 0.29 0.64 0.46 0.92 0.24 0.65 0.33 0.45 0.46 1 1 1,2 2,4 2 1, 2 1,4,6 2, 5, 6, 7, 8 1,2,3,4,5,6,7,8,9