Question: QUESTION 3 ( 2 0 Marks ) The project manager of Company X has identified the various activities required to complete his project. Use the

QUESTION 3(20 Marks)
The project manager of Company X has identified the various activities required to complete his project. Use
the information below to construct a network diagram (AON) for the project and determine its critical path.
Task/Number Duration (Days) Predecessors
A 15-
B 10 A
C 9 A
D 7 B
E 8 C, D
F 7 E
QUESTION 4(20 Marks)
You are monitoring a new product development project. Assess the progress of the project by using the
Earned value management method.
Use the information in the table to complete the calculations for A - D to assist in analysing the status of the
project.
Terms Values provided Values to be calculated
BAC Budget at Completion R60000
PV Planned Value A
PC Percentage Complete 50%
EV Earned Value B
AC Actual Cost R20000
SV Schedule Variance C
CV Cost Variance D
The project should be 60% complete at this stage.
QUESTION 5(20 Marks)
A few issues may arise during the project closure phase therefore, a project closure process should be
followed. Formulate a guideline that project managers could use to close their projects comprehensively
 QUESTION 3(20 Marks) The project manager of Company X has identified

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!