Question: QUESTION 3 ( 2 0 Marks ) The project manager of Company x has identified the various activities required to complete his project. Use the

QUESTION 3
(20 Marks)
The project manager of Company x has identified the various activities required to complete his project. Use the information below to construct a network diagram (AON) for the project and determine its critical path.
\table[[Task/Number,Duration (Days),Predecessors],[A,15,-],[B,10,A],[C,9,A],[D,7,B],[E,8,C, D],[F,7,E]]