A facility is setting up an assembly line to produce 60 units per day, working 16 hours per day.
\table[[Task,Time (Min),Predecessors],[A,4,-],[B,8,-],[C,3,A],[D,8,A,B],[E,4,C,D]]
(a)[2 Points] What is the desired cycle time for the assembly line? (round to whole number) ANSWER:
(b)[3 Points] What is the theoretical minimum # of workstations? (round to whole number) ANSWER:
(c)[10 points] Balance the line and assign tasks to workstations using the longest task time rule. Break ties with the most number of followers rule. (Use the chart & process presented in class)
(d)[2 points] What is the actual cycle time of the balanced layout above? (2 decimal places) ANSWER:
(e)[3 Points] What is the cycle idle time per unit of the balanced line? (2 decimal places) ANSWER:
 Question 3-[20 Points] A facility is setting up an assembly line

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!