Question: Question 3 2 0 pts A project being analyzed by PERT has 6 0 activities, 1 3 of which are on the critical path. If

Question 3
20 pts
A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 81, what is the probability that the project will take 218 days or more to complete?
Choose the closest number.
0.1587
0.3283
0.8413
0.0126
0.6716
 Question 3 20 pts A project being analyzed by PERT has

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!