Question (3)(25 marks)
A part requires three processing steps on three machines in the sequence \(\mathrm{A}-\mathrm{B}\cdot \mathrm{C}\). The demand for this part is 10,000 units per week. The company operates six days per week, eight hours per day. Given the following performance data, answer the following questions:
- Calculate the number of parts processed per week in each operation. and find the number of machines A,B,C needed to meet the market demand