Question: Question 3 ) ( 2 5 points ) The performance of a project was evaluated 1 0 weeks after its start. Table gives the relevant

Question 3)(25 points) The performance of a project was evaluated 10 weeks after its start. Table gives the relevant information. Discuss the project performance with the details given for each organizational unit U1 and U2 and for the project as a whole.
\table[[Activity,Pred.,\table[[Normal Time],[(week)]],\table[[Budget],[(S)]],\table[[Organization],[Unit]],\table[[Percent],[Complete]],\table[[Money Spent],[($)]]],[A,-,4,90,U1,100,110],[B,A,2,35,U2,100,20],[C,A,6,75,U2,40,40],[D,B,3,60,U1,80,90],[E,C,10,80,U1,0,0]]