Question: Question 3 (25 marks) A project set to last seven months contains eight major tasks with costs and timings shown below. Task Earliest start [week

Question 3 (25 marks)

A project set to last seven months contains eight major tasks with costs and timings shown below.

Task

Earliest start [week number]

Duration in weeks

Cost

1

0

8

10,000

2

2

16

12,000

3

8

10

2,500

4

8

6

6,000

5

10

12

6,000

6

14

6

9,000

7

18

8

2,000

8

20

8

3,000

Table 1

Assume an even spend rate in each task.

At the end of month 3 the position of the project in terms of assessed and actual expenditure is shown in Table 2 below:

Task No

ACWP

% Complete

1

9,500

100

2

9,800

45

3

1,200

10

4

1,700

15

5

2,100

20

TOTAL

24,300

49

Table 2

Using Earned value techniques:

  1. Using the information provided in Table 1 prepare a master programme for the project and then indicate its progress to date using the information provided in Table 2. [7 marks]
  2. Calculate the project performance to date. Discuss the likely outcome for the project at completion if performance remains unchanged [12 marks]
  3. Indicate graphically the earned value, budget and actual cost figures week by week. On the same graph demonstrate the SV and CV figures. [6 marks]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!