Question: Question 3 (25 marks) A project set to last seven months contains eight major tasks with costs and timings shown below. Task Earliest start [week
Question 3 (25 marks)
A project set to last seven months contains eight major tasks with costs and timings shown below.
| Task | Earliest start [week number] | Duration in weeks | Cost |
| 1 | 0 | 8 | 10,000 |
| 2 | 2 | 16 | 12,000 |
| 3 | 8 | 10 | 2,500 |
| 4 | 8 | 6 | 6,000 |
| 5 | 10 | 12 | 6,000 |
| 6 | 14 | 6 | 9,000 |
| 7 | 18 | 8 | 2,000 |
| 8 | 20 | 8 | 3,000 |
Table 1
Assume an even spend rate in each task.
At the end of month 3 the position of the project in terms of assessed and actual expenditure is shown in Table 2 below:
| Task No | ACWP | % Complete |
| 1 | 9,500 | 100 |
| 2 | 9,800 | 45 |
| 3 | 1,200 | 10 |
| 4 | 1,700 | 15 |
| 5 | 2,100 | 20 |
| TOTAL | 24,300 | 49 |
Table 2
Using Earned value techniques:
- Using the information provided in Table 1 prepare a master programme for the project and then indicate its progress to date using the information provided in Table 2. [7 marks]
- Calculate the project performance to date. Discuss the likely outcome for the project at completion if performance remains unchanged [12 marks]
- Indicate graphically the earned value, budget and actual cost figures week by week. On the same graph demonstrate the SV and CV figures. [6 marks]
Step by Step Solution
There are 3 Steps involved in it